Goodman Property Services | Warehouse Switchboard Installation | Rewiring


Client:

Goodman Property Services


Location:

Building 4, 1508 Centre Road, Clayton VIC


Case Study

Prolux brought this huge condemned warehouse at Clayton Business Park back to life.


The factory at Building 4 spans an impressive 54,000m2, but had been left dormant for several years. It was unknow that one of the HV substations feeding the building was inoperable due to water egress within. This lead to 90% of the building to be rewired and with traces of asbestos found within the building itself, the method of installation wasn’t straight forward. Prolux were able to work within the correct guidelines to safely complete the project within a 3 week time frame.


The initial site visit commenced with design and consultation to facilitate the provision of Preliminary Plans for emergency and exit lighting; over 190 exit and emergency lights were installed, including test switches to switchboards as required.


The warehouse electrical rewiring was completed to facilitate the LED upgrade of over 300 LED High bay lights, including catenary cable support and a new switchboard to ensure the safe installation of additional lighting circuits.


Upgrading the existing switchboard infrastructure to meet current AS3000 Standards and the client’s national RCD roll-out program was priority; in total nine new switchboards were installed along with several hundred RCBO’s.

by Alex Lamblin 04 Feb, 2024
Client: Schneider Electric
11 Jan, 2024
Client: Dexus Property Group
11 Jan, 2024
Client: Goodman
by Dom Dedic 11 Jan, 2024
Client: Heritage Bank
11 Jan, 2024
Client: Cricket Australia
11 Jan, 2024
Client: The Sorbent Paper Co.
11 Jan, 2024
Client: Mercedes-Benz
11 Jan, 2024
Client: Australian Automotive Distribution
More Case Studies
Share by: