Case Study:
Client: eNett International (former PSP Corporation)
Site: 50 Queen Street, Melbourne
Problem:
Occupying Level 13, PSP Corporation expanded, taking residence of Level 12 and required new workstations to be set up for new staff commencing work within days. With limited space, finding room for them had fast become an issue. New data cabling and power outlets had to be wired and installed, along with existing points to be tested. PSP Corporation did not have the time to arrange quotes from builders and furniture contractors to create a workable space; the whole process was managed internally in a matter of days.
Scope of Works:
Wire all workstations; data cabling and power outlets:
- Wiring and installation of dual CAT6 data outlets and dual power supply to each workstation
- General data and power for photo copier rooms, flat screen display panels, cleaning areas and workstations
- Wiring and installation of dedicated GPOs for the communications rack
- Installation of the communications rack for customer’s IT equipment and all fixed data cabling to terminate
- Supply and installation of new patch panels and WIFI points
Supply and installation of data and communication tie cables between the existing customer’s rack on Level 13 and the new rack on Level 12.
“We are proud of our achievements in electrical safety and quality, consistently providing the highest level of workmanship is what we do.”
Identify Solutions:
Prolux Electrical Contractors, the base building contractor were asked by the tenant to install a complete data network and power solution to the workstations they were having installed. The challenge was that it needed to be completed prior to their new staff commencing. This gave Prolux two days; one day for preparing the project and ordering all required parts and one day for installing and testing all components.
Conclude and Recommend:
Within days of the client contacting Prolux, Alex had been out to site, quoted for all works to be undertaken and had the job completed on time and within budget. The staff at PSP Corporation were able to move in to their new workstations straight away, with no interruption to their work schedule.
For more information, or a detailed analysis on your building’s requirements, call Prolux for a no obligation, free building appraisal.